— Project Summary

Queue ID
SPP-GEN-2024-061
Capacity
200 MW
Technology
Battery
Status
active
Location
Cowley, KS
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveBatterySPPLBNL + Live

200 MW storage in Cowley, KS · In queue since October 2024 · Proposed COD December 2028

200 MW

Capacity

1

Components

Battery

1y 5m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 2m

Impact Study25%
Queue EntryOct 30, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

KS

County

Cowley

Region

SPP

Developer

Utility

WERE

Entity

SPP

Point of Interconnection

Creswell 138 kV Substation

Data Source

LBNL + Live

No news available for this project.