— Project Summary

Queue ID
SPP-GEN-2024-054
Capacity
120 MW
Technology
Solar
Status
active
Location
Cooper, MO
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

120 MW generation in Cooper, MO · In queue since October 2024 · Proposed COD December 2029

120 MW

Capacity

1

Components

Solar

1y 5m

In Queue

System Impact Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 2m

Impact Study25%
Queue EntryOct 30, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-31

Project Details

State

MO

County

Cooper

Region

SPP

Developer

Utility

WERE

Entity

SPP

Point of Interconnection

Overton - Sedalia East 161 kV line

Data Source

LBNL + Live

No news available for this project.