BetaActiveSolarSPPLBNL + Live
120 MW generation in Cooper, MO · In queue since October 2024 · Proposed COD December 2029
120 MW
Capacity
1
Components
Solar
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 2m
Impact Study25%
Queue EntryOct 30, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
MO
County
Cooper
Region
SPP
Developer
—
Utility
WERE
Entity
SPP
Point of Interconnection
Overton - Sedalia East 161 kV line
Data Source
LBNL + Live
No news available for this project.