170 MW storage in Lancaster, NE · In queue since October 2024 · Proposed COD May 2028
170 MW
Capacity
1
Components
Battery
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 7m
Impact Study25%
Queue EntryOct 30, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-17
Project Details
State
NE
County
Lancaster
Region
SPP
Developer
—
Utility
LES
Entity
SPP
Point of Interconnection
Waverly 115 kV Substation
Data Source
LBNL + Live