— Project Summary

Queue ID
SPP-GEN-2024-050
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Castro, TX
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarBatterySPPLBNL + Live

300 MW hybrid in Castro, TX · In queue since October 2024 · Proposed COD December 2028

300 MW

Capacity

1

Components

Solar

1y 5m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 2m

Impact Study25%
Queue EntryOct 30, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

TX

County

Castro

Region

SPP

Developer

Utility

SPS

Entity

SPP

Point of Interconnection

Deaf Smith - Plant X 230 kV line

Data Source

LBNL + Live

No news available for this project.