— Project Summary

Queue ID
SPP-GEN-2024-044
Capacity
36 MW
Technology
Solar
Status
active
Location
Caddo Parish, LA
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

36 MW generation in Caddo Parish, LA · In queue since October 2024 · Proposed COD July 2027

36 MW

Capacity

1

Components

Solar

1y 5m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

2y 9m

Impact Study25%
Queue EntryOct 30, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-01

Project Details

State

LA

County

Caddo Parish

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Hosston - Plain Dealing 69 kV Line

Data Source

LBNL + Live

No news available for this project.