BetaActiveWindSPPLBNL + Live
250 MW generation in Floyd, TX · In queue since October 2024 · Proposed COD December 2029
250 MW
Capacity
1
Components
Wind
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 2m
Impact Study25%
Queue EntryOct 30, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
TX
County
Floyd
Region
SPP
Developer
—
Utility
SPS
Entity
SPP
Point of Interconnection
Tuco - Oklaunion 345 kV Line
Data Source
LBNL + Live
No news available for this project.