BetaActiveBatterySPPLBNL + Live
175 MW storage in Sargent, ND · In queue since October 2024 · Proposed COD July 2029
175 MW
Capacity
1
Components
Battery
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 9m
Impact Study25%
Queue EntryOct 30, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
ND
County
Sargent
Region
SPP
Developer
—
Utility
WAPA
Entity
SPP
Point of Interconnection
Forman 115 kV Substation
Data Source
LBNL + Live