BetaActiveWindSPPLBNL + Live
300 MW generation in Smith, KS · In queue since October 2024 · Proposed COD December 2028
300 MW
Capacity
1
Components
Wind
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 2m
Impact Study25%
Queue EntryOct 30, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-29
Project Details
State
KS
County
Smith
Region
SPP
Developer
—
Utility
ITCGP
Entity
SPP
Point of Interconnection
Post Rock - Axtell 345 kV Line
Data Source
LBNL + Live
No news available for this project.