— Project Summary

Queue ID
SPP-GEN-2024-007
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Stafford, KS
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarBatterySPPLBNL + Live

80 MW hybrid in Stafford, KS · In queue since April 2024 · Proposed COD December 2028

80 MW

Capacity

1

Components

Solar

1y 11m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 8m

Impact Study25%
Queue EntryApr 30, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

KS

County

Stafford

Region

SPP

Developer

Utility

MIDW

Entity

SPP

Point of Interconnection

Seward 115 kV Substation

Data Source

LBNL + Live

No news available for this project.