102.2 MW generation in Franklin, AR · In queue since April 2024 · Proposed COD November 2025
102.2 MW
Capacity
1
Components
Gas
1y 11m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 7m
Schedule
5 months past proposed COD
Impact Study25%
Queue EntryApr 25, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-07
Project Details
State
AR
County
Franklin
Region
SPP
Developer
—
Utility
AECC
Entity
SPP
Point of Interconnection
Fitzhugh 161kV
Data Source
LBNL + Live