BetaActiveBatterySPPLBNL + Live
135 MW storage in Wayne, NE · In queue since December 2022 · Proposed COD December 2024
135 MW
Capacity
1
Components
Battery
3y 3m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2 years
Schedule
15 months past proposed COD
Facilities Study50%
Queue EntryDec 16, 2022
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
NE
County
Wayne
Region
SPP
Developer
—
Utility
NPPD
Entity
SPP
Point of Interconnection
Hoskins 345 kV Substation
Data Source
LBNL + Live
No news available for this project.