BetaActiveBatterySPPLBNL + Live
72.5 MW storage in Mayes, OK · In queue since July 2023 · Proposed COD December 2024
72.5 MW
Capacity
1
Components
Battery
2y 8m
In Queue
IA Pending
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 5m
Schedule
16 months past proposed COD
In Study38%
Queue EntryJul 12, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-09
Project Details
State
OK
County
Mayes
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Pryor Junction 138kV sub
Data Source
LBNL + Live
No news available for this project.