BetaActiveBatterySPPLBNL + Live
124.7 MW storage in Mayes, OK · In queue since June 2023 · Proposed COD December 2024
124.7 MW
Capacity
1
Components
Battery
2y 9m
In Queue
IA Pending
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 6m
Schedule
16 months past proposed COD
In Study38%
Queue EntryJun 20, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-06
Project Details
State
OK
County
Mayes
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Explorer Claremore Tap COOYYAH4
Data Source
LBNL + Live