BetaActiveSolarBatterySPPLBNL + Live
150 MW hybrid in Bossier Parish, LA · In queue since October 2023 · Proposed COD November 2028
150 MW
Capacity
1
Components
Solar
2y 5m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 1m
Impact Study25%
Queue EntryOct 2, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-19
Project Details
State
LA
County
Bossier Parish
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Red Pointe 138 kV Substation
Data Source
LBNL + Live