— Project Summary

Queue ID
SPP-GEN-2023-229
Capacity
230 MW
Technology
Wind
Status
active
Location
Caddo, OK
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveWindSPPLBNL + Live

230 MW generation in Caddo, OK · In queue since October 2023 · Proposed COD October 2028

230 MW

Capacity

1

Components

Wind

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5 years

Impact Study25%
Queue EntryOct 2, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-31

Project Details

State

OK

County

Caddo

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Southwestern Power Station 138 kV Substation (SWS4)

Data Source

LBNL + Live

No news available for this project.