— Project Summary

Queue ID
SPP-GEN-2023-225
Capacity
217 MW
Technology
Gas
Status
active
Location
Lancaster, NE
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveGasSPPLBNL + Live

217 MW generation in Lancaster, NE · In queue since October 2023 · Proposed COD June 2027

217 MW

Capacity

1

Components

Gas

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 8m

Impact Study25%
Queue EntryOct 2, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

NE

County

Lancaster

Region

SPP

Developer

Utility

NPPD

Entity

SPP

Point of Interconnection

Olive Creek 345 kV Substation

Data Source

LBNL + Live

No news available for this project.