BetaActiveGasSPPLBNL + Live
478 MW generation in Gage, NE · In queue since October 2023 · Proposed COD June 2027
478 MW
Capacity
1
Components
Gas
2y 5m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
Impact Study25%
Queue EntryOct 2, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
NE
County
Gage
Region
SPP
Developer
—
Utility
NPPD
Entity
SPP
Point of Interconnection
New Beatrice Power Station 345 kV
Data Source
LBNL + Live
No news available for this project.