BetaActiveSolarBatterySPPLBNL + Live
250 MW hybrid in Dakota, NE · In queue since October 2023 · Proposed COD March 2027
250 MW
Capacity
1
Components
Solar
2y 5m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Impact Study25%
Queue EntryOct 2, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-28
Project Details
State
NE
County
Dakota
Region
SPP
Developer
—
Utility
NPPD
Entity
SPP
Point of Interconnection
Twin Church 230 kV Substation
Data Source
LBNL + Live
No news available for this project.