— Project Summary

Queue ID
SPP-GEN-2023-199
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Dakota, NE
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarBatterySPPLBNL + Live

250 MW hybrid in Dakota, NE · In queue since October 2023 · Proposed COD March 2027

250 MW

Capacity

1

Components

Solar

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 5m

Impact Study25%
Queue EntryOct 2, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-28

Project Details

State

NE

County

Dakota

Region

SPP

Developer

Utility

NPPD

Entity

SPP

Point of Interconnection

Twin Church 230 kV Substation

Data Source

LBNL + Live

No news available for this project.