— Project Summary

Queue ID
SPP-GEN-2023-170
Capacity
150 MW
Technology
Battery
Status
active
Location
Chariton, MO
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveBatterySPPLBNL + Live

150 MW storage in Chariton, MO · In queue since October 2023 · Proposed COD June 2028

150 MW

Capacity

1

Components

Battery

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 8m

Impact Study25%
Queue EntryOct 2, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

MO

County

Chariton

Region

SPP

Developer

Utility

Evergy

Entity

SPP

Point of Interconnection

Salisbury 161 kV Substation

Data Source

LBNL + Live

No news available for this project.