— Project Summary

Queue ID
SPP-GEN-2023-099
Capacity
300 MW
Technology
Solar
Status
active
Location
Jackson, KS
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

300 MW generation in Jackson, KS · In queue since October 2023 · Proposed COD December 2030

300 MW

Capacity

1

Components

Solar

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7y 2m

Impact Study25%
Queue EntryOct 2, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-31

Project Details

State

KS

County

Jackson

Region

SPP

Developer

Utility

Evergy

Entity

SPP

Point of Interconnection

Jeffery Energy Center 345 kV Substation

Data Source

LBNL + Live