— Project Summary

Queue ID
SPP-GEN-2023-088
Capacity
117 MW
Technology
Wind
Status
active
Location
Okfuskee, OK
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveWindSPPLBNL + Live

117 MW generation in Okfuskee, OK · In queue since October 2023 · Proposed COD December 2028

117 MW

Capacity

1

Components

Wind

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 2m

Impact Study25%
Queue EntryOct 2, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

OK

County

Okfuskee

Region

SPP

Developer

Utility

WFEC

Entity

SPP

Point of Interconnection

Pharaoh 138 kV Substation

Data Source

LBNL + Live

No news available for this project.