BetaActiveGasSPPLBNL + Live
255 MW generation in Cass, NE · In queue since October 2023 · Proposed COD February 2028
255 MW
Capacity
1
Components
Gas
2y 5m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 4m
Impact Study25%
Queue EntryOct 2, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-02-01
Project Details
State
NE
County
Cass
Region
SPP
Developer
—
Utility
OPPD
Entity
SPP
Point of Interconnection
Substation 3740 345 kV
Data Source
LBNL + Live
No news available for this project.