— Project Summary

Queue ID
SPP-GEN-2023-078
Capacity
255 MW
Technology
Gas
Status
active
Location
Cass, NE
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveGasSPPLBNL + Live

255 MW generation in Cass, NE · In queue since October 2023 · Proposed COD February 2028

255 MW

Capacity

1

Components

Gas

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

Impact Study25%
Queue EntryOct 2, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-02-01

Project Details

State

NE

County

Cass

Region

SPP

Developer

Utility

OPPD

Entity

SPP

Point of Interconnection

Substation 3740 345 kV

Data Source

LBNL + Live

No news available for this project.