— Project Summary

Queue ID
SPP-GEN-2023-059
Capacity
200 MW
Technology
Solar
Status
active
Location
Harrison, TX
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarGasSPPLBNL + Live

200 MW hybrid in Harrison, TX · In queue since September 2023 · Proposed COD December 2026

200 MW

Capacity

1

Components

Solar

2y 6m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 3m

Impact Study25%
Queue EntrySep 11, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

TX

County

Harrison

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Tap Rockhill to South Shreveport 138 kV line

Data Source

LBNL + Live

No news available for this project.