BetaActiveSolarGasSPPLBNL + Live
200 MW hybrid in Harrison, TX · In queue since September 2023 · Proposed COD December 2026
200 MW
Capacity
1
Components
Solar
2y 6m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 3m
Impact Study25%
Queue EntrySep 11, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Harrison
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Tap Rockhill to South Shreveport 138 kV line
Data Source
LBNL + Live
No news available for this project.