— Project Summary

Queue ID
SPP-GEN-2023-034
Capacity
130 MW
Technology
Solar
Status
active
Location
Sedgwick, KS
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

130 MW generation in Sedgwick, KS · In queue since October 2023 · Proposed COD September 2026

130 MW

Capacity

1

Components

Solar

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 11m

Impact Study25%
Queue EntryOct 2, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-01

Project Details

State

KS

County

Sedgwick

Region

SPP

Developer

Utility

Evergy

Entity

SPP

Point of Interconnection

Clear Water - Waco 138 kV line

Data Source

LBNL + Live