— Project Summary

Queue ID
SPP-GEN-2022-176
Capacity
215 MW
Technology
Wind
Status
active
Location
Nowata, OK
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveWindSPPLBNL + Live

215 MW generation in Nowata, OK · In queue since February 2023 · Proposed COD October 2026

215 MW

Capacity

1

Components

Wind

3y 1m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

Impact Study25%
Queue EntryFeb 17, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-31

Project Details

State

OK

County

Nowata

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Northeastern - Delaware 345 kV transmission line

Data Source

LBNL + Live

No news available for this project.