BetaActiveWindSPPLBNL + Live
215 MW generation in Nowata, OK · In queue since February 2023 · Proposed COD October 2026
215 MW
Capacity
1
Components
Wind
3y 1m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 8m
Impact Study25%
Queue EntryFeb 17, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-31
Project Details
State
OK
County
Nowata
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Northeastern - Delaware 345 kV transmission line
Data Source
LBNL + Live
No news available for this project.