203 MW generation in Hale, TX · In queue since February 2023 · Proposed COD April 2025
203 MW
Capacity
1
Components
Gas
3y 1m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 2m
Schedule
12 months past proposed COD
Impact Study25%
Queue EntryFeb 21, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-04-15
Project Details
State
TX
County
Hale
Region
SPP
Developer
—
Utility
SPS
Entity
SPP
Point of Interconnection
Tuco 345kV
Data Source
LBNL + Live