— Project Summary

Queue ID
SPP-GEN-2022-142
Capacity
200 MW
Technology
Battery
Status
active
Location
Clay, MO
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveBatterySPPLBNL + Live

200 MW storage in Clay, MO · In queue since February 2023 · Proposed COD December 2027

200 MW

Capacity

1

Components

Battery

3y 1m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 10m

Impact Study25%
Queue EntryFeb 21, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

MO

County

Clay

Region

SPP

Developer

Utility

KCPL

Entity

SPP

Point of Interconnection

Shoal Creek 161 kV Substation

Data Source

LBNL + Live