— Project Summary

Queue ID
SPP-GEN-2022-139
Capacity
300 MW
Technology
Battery
Status
active
Location
Harrison, TX
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveBatterySPPLBNL + Live

300 MW storage in Harrison, TX · In queue since February 2023 · Proposed COD December 2027

300 MW

Capacity

1

Components

Battery

3y 1m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 10m

Impact Study25%
Queue EntryFeb 21, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

TX

County

Harrison

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Pirkey 345kV Substation

Data Source

LBNL + Live

No news available for this project.