BetaActiveSolarSPPLBNL + Live
113.078 MW generation in Bryan, OK · In queue since January 2023 · Proposed COD February 2026
113.078 MW
Capacity
1
Components
Solar
3y 2m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 1m
Schedule
2 months past proposed COD
Impact Study25%
Queue EntryJan 26, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-02
Project Details
State
OK
County
Bryan
Region
SPP
Developer
—
Utility
WFEC
Entity
SPP
Point of Interconnection
Brown - South Coleman Junction 138kV line
Data Source
LBNL + Live