— Project Summary

Queue ID
SPP-GEN-2022-104
Capacity
113.078 MW
Technology
Solar
Status
active
Location
Bryan, OK
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

113.078 MW generation in Bryan, OK · In queue since January 2023 · Proposed COD February 2026

113.078 MW

Capacity

1

Components

Solar

3y 2m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 1m

Schedule

2 months past proposed COD

Impact Study25%
Queue EntryJan 26, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-02

Project Details

State

OK

County

Bryan

Region

SPP

Developer

Utility

WFEC

Entity

SPP

Point of Interconnection

Brown - South Coleman Junction 138kV line

Data Source

LBNL + Live

No news available for this project.