BetaActiveSolarBatterySPPLBNL + Live
80 MW hybrid in Cooper, MO · In queue since March 2023 · Proposed COD October 2026
80 MW
Capacity
1
Components
Solar
3 years
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 7m
Impact Study25%
Queue EntryMar 24, 2023
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-01
Project Details
State
MO
County
Cooper
Region
SPP
Developer
—
Utility
KCPL
Entity
SPP
Point of Interconnection
Overton - Sedalia East 161 kV Substation
Data Source
LBNL + Live
No news available for this project.