— Project Summary

Queue ID
SPP-GEN-2022-075
Capacity
175 MW
Technology
Solar
Status
active
Location
Ellis, KS
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

175 MW generation in Ellis, KS · In queue since September 2022 · Proposed COD November 2027

175 MW

Capacity

1

Components

Solar

3y 6m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 2m

Impact Study25%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-19

Project Details

State

KS

County

Ellis

Region

SPP

Developer

Utility

ITCGP

Entity

SPP

Point of Interconnection

Tap on the Spearville - Post Rock 345kV line

Data Source

LBNL + Live