— Project Summary

Queue ID
SPP-GEN-2022-071
Capacity
90.824 MW
Technology
Solar
Status
active
Location
Pittsburg, OK
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

90.824 MW generation in Pittsburg, OK · In queue since August 2022 · Proposed COD February 2026

90.824 MW

Capacity

1

Components

Solar

3y 7m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 6m

Schedule

2 months past proposed COD

Impact Study25%
Queue EntryAug 12, 2022

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-02

Project Details

State

OK

County

Pittsburg

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Talawanda to Canadian River 138 kV Line Tap

Data Source

LBNL + Live

No news available for this project.