BetaActiveSolarSPPLBNL + Live
90.824 MW generation in Pittsburg, OK · In queue since August 2022 · Proposed COD February 2026
90.824 MW
Capacity
1
Components
Solar
3y 7m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 6m
Schedule
2 months past proposed COD
Impact Study25%
Queue EntryAug 12, 2022
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-02
Project Details
State
OK
County
Pittsburg
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Talawanda to Canadian River 138 kV Line Tap
Data Source
LBNL + Live
No news available for this project.