BetaActiveSolarSPPLBNL + Live
145 MW generation in Edwards, KS · In queue since July 2022 · Proposed COD November 2027
145 MW
Capacity
1
Components
Solar
3y 8m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 4m
Impact Study25%
Queue EntryJul 25, 2022
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-19
Project Details
State
KS
County
Edwards
Region
SPP
Developer
—
Utility
SUNC
Entity
SPP
Point of Interconnection
tap on Arthur Mullergreen-Spearville 230 kV line
Data Source
LBNL + Live
No news available for this project.