— Project Summary

Queue ID
SPP-GEN-2022-065
Capacity
145 MW
Technology
Solar
Status
active
Location
Edwards, KS
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

145 MW generation in Edwards, KS · In queue since July 2022 · Proposed COD November 2027

145 MW

Capacity

1

Components

Solar

3y 8m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 4m

Impact Study25%
Queue EntryJul 25, 2022

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-19

Project Details

State

KS

County

Edwards

Region

SPP

Developer

Utility

SUNC

Entity

SPP

Point of Interconnection

tap on Arthur Mullergreen-Spearville 230 kV line

Data Source

LBNL + Live

No news available for this project.