— Project Summary

Queue ID
SPP-GEN-2022-055
Capacity
200 MW
Technology
Solar
Status
active
Location
Grady, OK
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

200 MW generation in Grady, OK · In queue since June 2022 · Proposed COD December 2025

200 MW

Capacity

1

Components

Solar

3y 9m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 6m

Schedule

3 months past proposed COD

Impact Study25%
Queue EntryJun 23, 2022

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

OK

County

Grady

Region

SPP

Developer

Utility

WFEC

Entity

SPP

Point of Interconnection

Sunshine North to Anadarko 138 kV

Data Source

LBNL + Live

No news available for this project.