BetaActiveSolarSPPLBNL + Live
200 MW generation in Grady, OK · In queue since June 2022 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
3y 9m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 6m
Schedule
3 months past proposed COD
Impact Study25%
Queue EntryJun 23, 2022
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
OK
County
Grady
Region
SPP
Developer
—
Utility
WFEC
Entity
SPP
Point of Interconnection
Sunshine North to Anadarko 138 kV
Data Source
LBNL + Live
No news available for this project.