BetaActiveSolarSPPLBNL + Live
33 MW generation in Sedgwick, KS · In queue since May 2022 · Proposed COD October 2026
33 MW
Capacity
1
Components
Solar
3y 10m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 5m
Impact Study25%
Queue EntryMay 26, 2022
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-31
Project Details
State
KS
County
Sedgwick
Region
SPP
Developer
—
Utility
WERE
Entity
SPP
Point of Interconnection
Murray Gill 138 kV Substation
Data Source
LBNL + Live
No news available for this project.