BetaActiveWindSPPLBNL + Live
504 MW generation in Hodgeman, KS · In queue since April 2021 · Proposed COD December 2027
504 MW
Capacity
1
Components
Wind
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 8m
Impact Study25%
Queue EntryApr 26, 2021
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
KS
County
Hodgeman
Region
SPP
Developer
—
Utility
SUNC
Entity
SPP
Point of Interconnection
SUNC Spearville - Holcomb 345kV
Data Source
LBNL + Live
No news available for this project.