200 MW storage in Titus, TX · In queue since April 2021 · Proposed COD May 2028
200 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 1m
Impact Study25%
Queue EntryApr 30, 2021
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-31
Project Details
State
TX
County
Titus
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Welsh 345kV Substation
Data Source
LBNL + Live
No news available for this project.