— Project Summary

Queue ID
SPP-GEN-2021-038
Capacity
200 MW
Technology
Battery
Status
active
Location
Titus, TX
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveBatterySPPLBNL + Live

200 MW storage in Titus, TX · In queue since April 2021 · Proposed COD May 2028

200 MW

Capacity

1

Components

Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 1m

Impact Study25%
Queue EntryApr 30, 2021

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-31

Project Details

State

TX

County

Titus

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Welsh 345kV Substation

Data Source

LBNL + Live

No news available for this project.