BetaActiveSolarSPPLBNL + Live
113 MW generation in Grant, KS · In queue since May 2021 · Proposed COD December 2026
113 MW
Capacity
1
Components
Solar
4y 10m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 7m
Impact Study25%
Queue EntryMay 14, 2021
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
KS
County
Grant
Region
SPP
Developer
—
Utility
SUNC
Entity
SPP
Point of Interconnection
Tap Sunflower Santana 115kV Transmission Line
Data Source
LBNL + Live
No news available for this project.