— Project Summary

Queue ID
SPP-GEN-2021-029
Capacity
253.8 MW
Technology
Battery
Status
active
Location
Linn, KS
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveBatterySPPLBNL + Live

253.8 MW storage in Linn, KS · In queue since May 2021 · Proposed COD December 2026

253.8 MW

Capacity

1

Components

Battery

4y 10m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 7m

Impact Study25%
Queue EntryMay 14, 2021

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

KS

County

Linn

Region

SPP

Developer

Utility

KCPL

Entity

SPP

Point of Interconnection

Evergy Tap the La Cygne to Stillwel 345 kV Line

Data Source

LBNL + Live

No news available for this project.