203.04 MW generation in Woodward, OK · In queue since May 2021 · Proposed COD December 2026
203.04 MW
Capacity
1
Components
Wind
4y 10m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 7m
Impact Study25%
Queue EntryMay 14, 2021
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
OK
County
Woodward
Region
SPP
Developer
—
Utility
WFEC
Entity
SPP
Point of Interconnection
Western Farmers 138kV Mooreland Substation
Data Source
LBNL + Live
No news available for this project.