— Project Summary

Queue ID
SPP-GEN-2021-006
Capacity
300 MW
Technology
Battery
Status
active
Location
Labette, KS
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveBatterySPPLBNL + Live

300 MW storage in Labette, KS · In queue since May 2021 · Proposed COD February 2026

300 MW

Capacity

1

Components

Battery

4y 10m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 9m

Schedule

2 months past proposed COD

Impact Study25%
Queue EntryMay 7, 2021

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-01

Project Details

State

KS

County

Labette

Region

SPP

Developer

Utility

WERE

Entity

SPP

Point of Interconnection

Neosho 345kV substation in Labette County, KS

Data Source

LBNL + Live

No news available for this project.