BetaActiveBatterySPPLBNL + Live
300 MW storage in Labette, KS · In queue since May 2021 · Proposed COD February 2026
300 MW
Capacity
1
Components
Battery
4y 10m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 9m
Schedule
2 months past proposed COD
Impact Study25%
Queue EntryMay 7, 2021
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-01
Project Details
State
KS
County
Labette
Region
SPP
Developer
—
Utility
WERE
Entity
SPP
Point of Interconnection
Neosho 345kV substation in Labette County, KS
Data Source
LBNL + Live