BetaActiveWindSPPLBNL + Live
352.5 MW generation in Terry, TX · In queue since April 2020 · Proposed COD December 2026
352.5 MW
Capacity
1
Components
Wind
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 8m
Impact Study25%
Queue EntryApr 24, 2020
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
TX
County
Terry
Region
SPP
Developer
—
Utility
SPS
Entity
SPP
Point of Interconnection
Tuco to Yoakum 345kV line
Data Source
LBNL + Live
No news available for this project.