— Project Summary

Queue ID
SPP-GEN-2020-067
Capacity
352.5 MW
Technology
Wind
Status
active
Location
Terry, TX
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveWindSPPLBNL + Live

352.5 MW generation in Terry, TX · In queue since April 2020 · Proposed COD December 2026

352.5 MW

Capacity

1

Components

Wind

5y 11m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6y 8m

Impact Study25%
Queue EntryApr 24, 2020

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

TX

County

Terry

Region

SPP

Developer

Utility

SPS

Entity

SPP

Point of Interconnection

Tuco to Yoakum 345kV line

Data Source

LBNL + Live