215 MW hybrid in Harlan, NE · In queue since April 2020 · Proposed COD June 2027
215 MW
Capacity
1
Components
Solar
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 2m
Impact Study25%
Queue EntryApr 10, 2020
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
NE
County
Harlan
Region
SPP
Developer
—
Utility
NPPD
Entity
SPP
Point of Interconnection
Orleans-Holdrege Substation 115kV
Data Source
LBNL + Live
No news available for this project.