— Project Summary

Queue ID
SPP-GEN-2020-012
Capacity
113 MW
Technology
Solar+Battery
Status
active
Location
Jackson, OK
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarBatterySPPLBNL + Live

113 MW hybrid in Jackson, OK · In queue since April 2020 · Proposed COD June 2027

113 MW

Capacity

1

Components

Solar

5y 11m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 2m

Impact Study25%
Queue EntryApr 10, 2020

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

OK

County

Jackson

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Snyder _x0013_ Altus Jct. 138kV

Data Source

LBNL + Live

No news available for this project.