BetaActiveWindSPPLBNL + Live
310 MW generation in Mcpherson, KS · In queue since May 2018 · Proposed COD May 2029
310 MW
Capacity
1
Components
Wind
7y 10m
In Queue
Suspended
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
11 years
In Study38%
Queue EntryMay 29, 2018
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-01
Project Details
State
KS
County
Mcpherson
Region
SPP
Developer
—
Utility
WERE
Entity
SPP
Point of Interconnection
Neosho 345kV Substation
Data Source
LBNL + Live
No news available for this project.