— Project Summary

Queue ID
SPP-GEN-2018-010
Capacity
74.1 MW
Technology
Battery
Status
active
Location
Montrail, ND
Region
SPP
Developer
IA Status
IA Executed

BetaActiveBatterySPPLBNL + Live

74.1 MW storage in Montrail, ND · In queue since April 2018 · Proposed COD December 2026

74.1 MW

Capacity

1

Components

Battery

7y 11m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

8y 8m

Construction75%
Queue EntryApr 27, 2018

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

ND

County

Montrail

Region

SPP

Developer

Utility

BEPC

Entity

SPP

Point of Interconnection

Neset 230kV Substation

Data Source

LBNL + Live

No news available for this project.