— Project Summary

Queue ID
SPP-GEN-2017-203
Capacity
210 MW
Technology
Solar
Status
active
Location
Grant, OK
Region
SPP
Developer
IA Status
Suspended

BetaActiveSolarSPPLBNL + Live

210 MW generation in Grant, OK · In queue since November 2017 · Proposed COD December 2026

210 MW

Capacity

1

Components

Solar

8y 4m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

9y 1m

In Study38%
Queue EntryNov 30, 2017

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

OK

County

Grant

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Renfrow 345kV Substation

Data Source

LBNL + Live

No news available for this project.