BetaActiveWindSPPLBNL + Live
400 MW generation in Oklahoma, OK · In queue since November 2017 · Proposed COD December 2028
400 MW
Capacity
1
Components
Wind
8y 4m
In Queue
Withdrawn
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
11y 1m
In Study38%
Queue EntryNov 22, 2017
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
OK
County
Oklahoma
Region
SPP
Developer
—
Utility
OGE
Entity
SPP
Point of Interconnection
Arcadia 345kV
Data Source
LBNL + Live