— Project Summary

Queue ID
SPP-GEN-2017-132
Capacity
400 MW
Technology
Wind
Status
active
Location
Oklahoma, OK
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

400 MW generation in Oklahoma, OK · In queue since November 2017 · Proposed COD December 2028

400 MW

Capacity

1

Components

Wind

8y 4m

In Queue

Withdrawn

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

11y 1m

In Study38%
Queue EntryNov 22, 2017

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

OK

County

Oklahoma

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Arcadia 345kV

Data Source

LBNL + Live

No news available for this project.