— Project Summary

Queue ID
SPP-GEN-2017-131
Capacity
29.6 MW
Technology
Battery
Status
active
Location
Wilson, KS
Region
SPP
Developer
IA Status
Suspended

BetaActiveBatterySPPLBNL + Live

29.6 MW storage in Wilson, KS · In queue since November 2017 · Proposed COD February 2026

29.6 MW

Capacity

1

Components

Battery

8y 4m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

8y 3m

Schedule

2 months past proposed COD

In Study38%
Queue EntryNov 22, 2017

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-01

Project Details

State

KS

County

Wilson

Region

SPP

Developer

Utility

WERE

Entity

SPP

Point of Interconnection

Altoona- NE Parson 138kV

Data Source

LBNL + Live

No news available for this project.