252 MW generation in Osage, KS · In queue since November 2017 · Proposed COD November 2027
252 MW
Capacity
1
Components
Wind
8y 4m
In Queue
Withdrawn
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
10 years
In Study38%
Queue EntryNov 20, 2017
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-08
Project Details
State
KS
County
Osage
Region
SPP
Developer
—
Utility
WERE
Entity
SPP
Point of Interconnection
Swissvale 345kV
Data Source
LBNL + Live